Talk About Scaffolding Screw Jack
Construction scaffolding screw jack for building stress transfer and adjustment of the ascent of the whole support, has the support stress transfer of stable and reliable, easy to rise buildings when the position offset etc., ADTO's production of building leadscrew variety, good quality and reasonable price.
2017-12-25 -
How To Determine The Damage Of Scaffold Coupler
The fatigue point of the construction scaffolding coupler caused the building to be overheated and the construction scaffolding coupler gap was too large, resulting in the middle of the construction scaffolding coupler.
2017-12-21 -
The Outlet For Scaffolding Couplers
In the face of constructional fastener industry product quality problem increasingly prominent, countries and strengthen product quality management, the new situation of fastener industry present situation and future development trend has carried on the comprehensive and thorough analysis, fully aware of the readjustment of the pneumatic fastener industry is an urgent and important task.
2017-12-19 -
Issues When Renting Scaffolding Couplers
Scaffolding couplers leasing process is indispensable equipment in modern construction, scaffolding couplers because of its special product line, a lot of construction enterprise is given priority to with the lease, this has given rise to the lease of the construction industry, so what kinds of problems will common rental agency encounter in scaffolding couplers?
2017-12-18 -
Differences Between Hot Dip Galvanizing And Cold Galvanizing
The main differences between hot dip galvanizing and cold galvanizing are as follows: 1. Unlike corrosion resistance, hot galvanizing is dozens of times that of cold galvanizing. 2. The method of operation is different: hot galvanizing is the zinc plating in the molten zinc of 450-480 degree, and the cold plating is zinc plated by electroplating or other methods at normal temperature. 3. The thickness of galvanized layer is different, and the thickness of hot galvanizing is much greater than that of cold galvanizing.
2017-12-15 -
The Characteristics Of Galvanized Scaffolding Tubes
The best advantage of galvanized pipe is that the current efficiency is as high as 100% and the deposition rate is fast, which is unmatched by other galvanized process. Due to the lack of detail in the coating, the dispersion ability and the deep plating ability are poor, so it is only suitable for electroplating such as tube materials and wire materials.
2017-12-12 -
The Maintanance Of Scaffolding Tubes
1. Investigate the vertical error of all or part of the scaffold, and investigate the side ports of the scaffold, whether it is inclined or not. If any abnormality is found, the personnel should be arranged for reinforcement immediately. 2. Check the bamboos on the mattress frequently, and timely fix broken bars and fill holes.
2017-12-10 -
The Set-up Requirements Of Frame Scaffolding
1. The inner and outer sides of the door frame should be cross-supported, and its dimensions should be matched with the spacing of the door frame and locked with the door frame. (1) the setting of the wall parts: if the frame is 45m below the height, it will be less than or equal to 6m. The frame is 45~ 60m, which is less than or equal to 4m (one at each level). The level is less than or equal to 6m and should comply with the specification.
2017-12-07 -
Security Technical Measures For Dismantling Of Frame Scaffold
(1) the scaffold should be ready before dismantling buildings on the surface of the product protection, debris and rubbish on the scaffold should be cleaned up, and has been careful scaffolding demolition scheme, safety technical disclosure to the relevant staff. Be alert and relevant.
2017-12-05 -
Secure Technical Measures To Set Up Frame Scaffold
1. When the scaffold is moving, it must be at a certain distance from the neighboring side and assign special person to look after; 2. In mobile, it is forbidden to start accelerating suddenly. 3. Check the scaffolding regularly, find the problems and hidden dangers, and repair and reinforce the construction timely before the construction work, so as to achieve solid and stable construction and ensure the safety of construction.
2017-12-04 -
Main Factors Affecting The Tubular Scaffolding Capacity
According to the relevant test materials, double row fastener type steel pipe scaffold overall stability test and the result of calculation and analysis, the excluded from the change of the load factor, the main factors influencing the scaffolding buckling bearing capacity as follows:
2017-11-30 -
Safety Management For Tubular Scaffolding
1. The scaffold personnel must be the professional scaffolds that are qualified according to the current national standard "safety technical assessment of special operations personnel" (GB5036). The staff should be examined regularly, and the qualified person will be able to hold the certificate.
2017-11-28 -
Tips You Should Know When Removing Tubular Scaffolding
1. Preparations for the removal of the scaffold shall meet the following requirements: (1) it is necessary to check whether the scaffold connection, the wall piece and the supporting system meet the structural requirements. (2) the removal sequence and measures in the design of the construction organization shall be supplemented and improved according to the inspection results, which can be implemented after approval by the competent department;
2017-11-27 -
Safe Standard For Cuplock Scaffolding System
Speaking of scaffolding, everyone should be familiar with it, especially in the construction industry. It is a kind of auxiliary equipment for building construction. There are many kinds of scaffolding, and the cuplock scaffold is one of the more advanced scaffolds on the market. Its joint construction is reasonable, the production process is very simple, and the operation is easy, the use scope is more extensive, can satisfy the construction requirement of a variety of buildings.
2017-11-23 -
Doule Row Outside Scaffolding
Using a Cuplock scaffold, it is convenient to set up two exclusive scaffolds, which can be quickly saved and quickly saved. It is especially suitable for setting up curved scaffolds and high-rise scaffolds. At present, the maximum height of the floor scaffold with "one rod to the top" (i.e. Scaffold full height using single pole) has reached 90.3 m.
2017-11-21