Procedure for using ADTO Formwork System can be divided into three parts:
A. PRE-CONCRETE ACTIVITIES
B. ON CONCRETE ACTIVITIES
C. POST CONCRETE ACTIVITIES
1. PRE – CONCRETE ACTIVITIES:
#1 Receipt of Equipment on Site – The equipment is received in the site as ordered.
#2 Level Surveys – Level checking is made to maintain a horizontal level check.
#3 Setting Out – The setting out of the formwork is done.
#4 Control / Correction of Deviation – Deviation or any correction is carried out.
#5 Erect Formwork – The formwork is erected on site.
#6 Erect Deck Formwork – Deck is erected for labors to work.
#7 Setting Kickers – kickers are provided over the beam.
2. ON CONCRETE ACTIVITIES:
#1 Dislodging of pins/wedges due to vibration.
#2 Beam/deck props adjacent to drop areas slipping due to vibration.
#3 Ensure all bracing at special areas slipping due to vibration.
#4 Overspill of concrete at window opening etc.
3. POST – CONCRETE ACTIVITIES:
#1 CLEANING:
• All components should be cleaned with scrapers and wire brushes as soon as they are struck. The wire brush is to be used on side rails only.
#2 TRANSPORTING:
• The heaviest and the longest, which is a full height of wall panel, can be carried up the nearest stairway. Passes through void areas.
#3 STRIKING:
• Once cleaned and transported to the next point of erection, panels should be stacked at the right place and in the right order.
#4 Erecting of Formwork:
• After that formwork is erect again on the next floor.