WHOLE SCAFFOLDING & FORMWORK SYSTEM (DESIGN) SERVICE SUPPLIER!

update
> ADTO News > What other advantages can you get from the ringlock scaffolding

Procedure For Using ADTO Formwork System

Time:2019/04/18

 

Procedure for using ADTO Formwork System can be divided into three parts:

 

A. PRE-CONCRETE ACTIVITIES

B. ON CONCRETE ACTIVITIES

C. POST CONCRETE ACTIVITIES

 

 

1. PRE – CONCRETE ACTIVITIES:

#1 Receipt of Equipment on Site – The equipment is received in the site as ordered.

#2 Level Surveys – Level checking is made to maintain a horizontal level check.

#3 Setting Out – The setting out of the formwork is done.

#4 Control / Correction of Deviation – Deviation or any correction is carried out.

#5 Erect Formwork – The formwork is erected on site.

#6 Erect Deck Formwork – Deck is erected for labors to work.

#7 Setting Kickers – kickers are provided over the beam.

 

 

2. ON CONCRETE ACTIVITIES:

#1 Dislodging of pins/wedges due to vibration.

#2 Beam/deck props adjacent to drop areas slipping due to vibration.

#3 Ensure all bracing at special areas slipping due to vibration.

#4 Overspill of concrete at window opening etc.

 

 

3. POST – CONCRETE ACTIVITIES:

#1 CLEANING:

• All components should be cleaned with scrapers and wire brushes as soon as they are struck. The wire brush is to be used on side rails only.

 

#2 TRANSPORTING:

• The heaviest and the longest, which is a full height of wall panel, can be carried up the nearest stairway. Passes through void areas.

 

#3 STRIKING:

• Once cleaned and transported to the next point of erection, panels should be stacked at the right place and in the right order.

 

#4 Erecting of Formwork:

• After that formwork is erect again on the next floor.

 

 

Related News