What Are the Factors to Remove the Cuplock Scaffolding Elements in the Project

Time:2018/05/24

1, dismantle field must be set up warning region, hanging eye-catching warning signs. Operators are strictly forbidden in the alert area of the passage or scaffold below continue to organize the construction. The ground monitoring personnel must perform their duties. High-rise building scaffolding demolished, should be equipped with good communication device.

 

 

scaffolding

 

 

 

2, carefully check the lifting machinery, including the rigging is safe and reliable. Lifting machinery is not allowed to build on the scaffolding, should be set separately.


3, such as the strong winds, rain, snow and other special climate, should not be for the removal of scaffolding, implementation of dismantling homework at night, should have good lighting.


4, building lock all the Windows must be closed in a cool, not allowed to open or to the overhanging objects.


5, after the demolition of personnel into the post, first check to reinforce the loose parts, clear steps within the layer of material, objects and garbage. Clear all things should be safety to the ground, forbidden from high toss.

6, according to the set-up of the program, the safety net - shaft block its protective railing joist - - inclined rod - even the wall - the ledger - small bar - bar.


7, do not allow the discrete surface to dismantle or upper and lower two step removed (step) at the same time. Seriously do it step by step, one rod.
8 and all the wall rod, inclined rod, not isolation, step up measures must with scaffolding layer removed, a simultaneous drop, no first dismantled.

 

 

scaffolding

 

9, rods and fasteners, in dismantling should be separated, do not allow the bar on fasteners to delivery, or two at the same time remove the ground.
10, all mat spread its demolition, should be erected in the outgoing, carry, prevent from the inside out, after the express garbage objects directly from the high fall injury.
 