The installation and upgrade process of overall climb outside scaffolding
The installation and upgrade process of overall climb outside scaffolding
→ → → erection truss erection of bearing the entire frame body set up to pull node → → A frame ceiling, hanging net → Install cantilever beam , electric hoist → Connect hoist and the load-bearing bottom bracket → Install anti- extraversion install anti-fall device → → inspection and acceptance.
2 ) to enhance the process:
Check hook → Loosen all fixed Rachel → evacuate to the frame of all live loads → short start hoist, hoist chain taut chain → adjust to make it even by force → Connection → Power lifting bearing bottom bracket removal and building observation synchronization situation → upgrade in place to provide the use of load-bearing bottom bracket installed → Install bearing end node → inspection and acceptance of the Torah .
During the use of the cantilever beam , electric hoist raised one level to prepare for the next upgrade scaffolding planks .
Each frame body to enhance a story high for a rise time of 1-2 hours.