ADTO News
Ten Steps to Check the Quality of RInglock Scaffolding for your Project
1, scaffolding foundation, foundation acceptance
1) ringlock scaffolding of groundwork and foundation construction, must according to the height of scaffolding, the erection site soil conditions is calculated in accordance with relevant regulations.
2) scaffolding whether solid groundwork and foundation
3) scaffolding whether level off ground foundation and the
4) scaffold in the foundation and basis whether water
2, the scaffolding ringlokck frame body drain acceptance
1) scaffold erection site debris removal, level off, and make the drainage unobstructed.
2) drain should be set in the scaffold outside the outside poling between 500 mm to 680 mm.
3) the width of the drain is: between 200 mm to 350 mm.Depth of: between 150 mm to 300 mm;A ditch end should be set set Wells (600 mm & times;600 mm & times;1200 mm) to ensure that the water in the ditch timely exclusion.
4) drain (width: 300 mm;The mouth width: 180 mm;
5) drain slope as I = 0.5
3, scaffolding plate, the acceptance of tap
1) scaffold plate, the acceptance of the tap is according to the height of scaffolding and carry to
2) 24 m is the scaffolding plate specification (width is greater than 200 mm, thickness is greater than 50 mm), ensure that every post must be put in the middle of the plate parts, plate area shall not be less than 0.15 m2
3) more than 24 m bearing scaffold at the bottom of the thickness of the plate must undergo strict calculation
4) scaffold tap must be placed in the center of the plate parts