Ringlock Scaffolding Building Standards and Application Skills
Ringlock type as a new type of scaffolding, scaffolding set-up is fast, safe, convenient, save material characteristics such as widely used in large-scale project construction, ringlock scaffolding should use the same elevation of beam bottom elevation range, for larger height and span of a single component bearing rack to pull bar and poling axial pressure calculating the critical force to ensure the stability of the frame body and safety.
A, Ringlock scaffold erection sequence and steps
1, in accordance with the site and layout size, put the adjustable base, and the adjustable base nut to roughly the same level;
2, install the vertical pole erected on the adjustable base, and in the same way the installation adjacent to a vertical rod;
3, will correspond to the span length of rail hooking in installed good promulgation and between ringlock button.
4, installation adjacent stud, at the same time, to bar hooking;
5, continue to install poling, bar hooking form four after poling a unit body;
6, use level, rotate the adjustable base, to build a good base for level adjustment;
7, will base level after the adjustment, the pursuit of root with corresponding ringlock scaffolding diagonal;
Second, the Ringlock type scaffold erection technology
1, no matter what type of erection of scaffolding, scaffold material and used in the processing quality, must conform to specified requirements is absolutely forbidden to use unqualified erection of scaffold materials, in case of accident.
2, general scaffolding must be scaffolding set-up, security technology operating rules for height more than 15 m or more tall scaffolding, must have the design, calculation and detailed, the erection scheme, technical director at the next higher level for examination and approval, have a written safety technical clarification, before the erection.