With the rapid development of construction industry, scaffolding, the price has become many scaffold construction personnel concerned topic. Scaffolding, in addition to the material cost, is labor cost, small makeup with all of you in the above article explained the construction scaffolding, how much money a square? For scaffolding costs also have a certain understanding. Today ADTO makes up and shares the scaffolding, artificial cost calculation, hope can help you. Scaffolding, artificial cost related knowledge:
1. The norm of the scaffold is compiled within 20 m high by building eaves, eaves high more than 20 m should be calculated when the scaffold material increase.
2. Eaves high scaffold materials increase the fees include: extend the amortized cost, scaffolding lifetime reinforcement. Scaffolding materials increase the all-in cost of use, no matter what actually happened, all this chapter shall prevail, not adjusted.
3. Eaves high more than 20 m scaffold materials increase the fee calculated on the following provisions.
(1) Eaves high part of the building shall be computed according to its more than part of the construction area.
(2) The higher storey height more than 3.6 m per 0.1 m according to the increase in the proportion of 1 m conversion (less than 0.1 m by 0.1 m), according to the corresponding project execution.
(3) Building eaves height more than 20 m high, but the highest one layer or one of the more than 20 m at the end of the floor, the floor is in more than 20 m part can only calculate every increase 1 m increase cost.
(4) In the same building there are two or more different cornice height, should according to the different height of the vertical section of a building area of applied subtitle accordingly.