ADTO News
Do You Know How to Erect and Remove the Ringlock Scaffolding
A ringlock type scaffold erection sequence and steps
1. In accordance with the site and layout size, put the adjustable base, and the adjustable base nut to roughly the same level;
2. Install the vertical pole erected on the adjustable base, and in the same way the installation adjacent to a vertical rod;
3. This will correspond to the span length of rail hooking in installed good promulgation and between the disk button.
4. Installation adjacent stud, at the same time, to bar hooking;
5. Continue to install poling, bar hooking form four after poling a unit body;
6. Use level or level, rotate the adjustable base, to build a good base for level adjustment;
How to erect the ringlock scaffolding by the right order
1. No matter what type of erection of scaffolding, scaffold material and used in the processing quality, must conform to specified requirements is absolutely forbidden to use unqualified erection of scaffold materials, in case of an accident.
2. General scaffolding must be scaffolding set-up, security technology operating rules for height more than 15 m or more tall scaffolding, must have the design, calculation and detailed, the erection scheme, technical director at the next higher level for examination and approval, have a written safety technical clarification, before the erection.
3. The risk for large ringlock scaffolding and special crane, pick, hang, socket, stacking shelves must also pass the design and the examination and approval. Prepare a separate safety technical measures, to build.
4. After the construction team to accept tasks, must organize personnel, carefully grasp the scaffold, special safety construction organization design and safety technical measures clarification, ringlock the erection method, and good technology, experienced technical personnel is responsible for the erection of technical guidance and supervision.