What Is the Criteria to Accept and Check the Frame Scaffolding
Height under the 20 m and 20 m scaffolding, project organization, head of the technology by the unit security personnel inspect acceptance; Height is more than 20 m scaffold by engineering technology with the progress of the organizational unit in stages, head of the project director and relevant acceptance technology security personnel to check.
1, the acceptance of frame scaffolding should possess the following documents:
The necessary construction design documents and assembly diagram; Scaffolding parts factory certification or quality grading qualified; Record and quality inspection of the scaffold construction; Major issues of the scaffold erection and processing records; The construction of the scaffold inspection report.
2, doors scaffold project acceptance, in addition to examine relevant documents, should also be on-site audit.
Selective examination should focus on the following, and construction acceptance report:
Whether security bar whether complete, the fastener tighten, qualified; Safety net hanging and armrest Settings are complete; Whether level off solid; Even the wall bar set ever missed, if they are complete and conform to the requirements; Verticality and levelness is qualified.
3, the levelness of the scaffold door:
Bottom step scaffolding deviation should be along the wall of the longitudinal level L / 600 or less (L is the length of the scaffold.
4, the size of the hot sales frame scaffolding, allowable deviation:
Scaffolding verticality: scaffolding deviation should be perpendicular to the vertical direction along the walls H / 400 or less for scaffolding height (H) and 50 mm; Scaffolding transverse vertical deviation of H / 600 and 50 mm or less; Each step of the longitudinal and transverse verticality deviation should be ho / 600 or less (h2 as the door height).