What Are the Erection Construction Scheme of Frame Scaffolding
Frame scaffold One, the erection of the preparation
1. Prepare the scaffold project construction organization design, requirements and contents are calculated fastener scaffold, see chapter 4 4.7.1.
2. The scaffold before the amnesty, technical managers should press frame scaffolding safety technical specification for construction of the building and construction group and the requirements of the design technical clarification to set up and use of personnel.
3. The steel frame accessories, strengthening inspection acceptance, it is prohibited to use unqualified components.
4. The scaffold erection site clean, neat, and good drainage.
Second, the erection of technical requirements
(a) foundation treatment
1. In order to ensure the foundation with sufficient carrying capacity, poling foundation construction should meet the requirements of 5.4.1 regulations and construction organization design; When on the floor structure, pick the scaffold erection, stud should be laid the foundation of the plate or block, and the floor or pick on mild structures, etc.
2. On the basis of scaffold should play the door frame stud position line, plate, base position accuracy.
(2) frame scaffolding procedures
Assembly: 1. The scaffold should extend from left side to the right side, step by step from bottom to top mounted, and can change the direction of the erection, step by step to reduce error accumulation, not the ends set-up or alternate with relative to one another to avoid dislocation junction, and difficult to connect.
2. The scaffolding, order:
Stow-wood laid (plate) - base was laid - since the side stood the door frame and then cross support to install level frame (or scaffolding), install the steel ladder to install horizontal reinforcing rod, according to the above steps in accordance with the provisions, position bridging step to assemble the top rail.