ADTO News
The Installation Details You Shall Pay Attention When Installing Scaffolding
Comprehensive detailed check ringlock scaffolding each link, the key to check whether the fastener connection is fixed, the supporting system meets the safety requirements, etc. According to the situation of the test results and site planning demolition scheme, and like the relevant departments of the declaration, is approved for demolition, to set up warning signs during the demolition, and should have specific personnel guards, avoid to cause dangerous.
First, when the demolition of frame must be demolished a specialist command, to do action coordination, moving in tandem, before that go through the formalities of approval, head of site construction.
Second, the ringlock type scaffolding demolition work area, the construction personnel are strictly prohibited.
Third, demolition order is quite important, first is removed after the erection of components, and then the build-up of the first part, it is important to note here is strictly forbidden on or pull down the demolition method.
Fourth, fixed thing to ringlock type scaffold removed one by one, when demolition to the last section riser, should look after the erection of temporary support reinforcement, can only be fixed with supporting parts.
Ringlock type scaffold fittings in the installation, to ensure the safety of using personnel during construction at the same time in order to ensure project to be carried out to normal, so take special attention, every detail is a link problems are likely to cause personnel casualties and engineering rout. Also, after completion of the construction, demolition of ringlock type foot hand accessories should be more attention, if a link error, consequence is unimaginable, so it is important to note.