Requirements on the Erection of Scaffolding Protection Measures for Working
1. The scaffolding work layer protection requirements
Scaffolding, scaffolding operation layer shall be put with scaffolding plank, board with board between close, leave the metope of 120 ~ 150 mm; When the gap between operation layer scaffold board and building is more than 150 mm, the protective measures should be taken.
Scaffolding shall generally be at least 2 layer, the upper layer for homework, lower for the protective layer. Only when setting a layer of scaffolding, should be in scaffold board sets along with the network layer. From the top job layer of the appropriate scaffold board down every 12 m spread a layer of scaffolding.
Protective railings and foot: all should build poling inside out; On the rail epithelial height should be 1.2 m; Block foot height is 180 mm; Rail should be centered in the setting.
Federated eye network, and network: scaffold poling inside, adopting dense mesh type safety net. Federated eye network must be conform to the requirements of the lashing, net around every 45 cm fastened on the scaffold tube. Building the first floor to set up the network, set up every three layer, operation layer consists of layer network. Blanket net will be adopted to meet the requirements of quality flat screen, and lashing fastened with no holes. Federated eye network, and pocket net seriously damaged, shall not be used.
2. Even the wall of a set of requirements
Even the wall except meet the requirements of computing the distance, there should be no greater than the largest spacing; Even the wall should be close to the master node set, deviating from the master node distance should be not more than 300 mm.