Procedure of ADTO Formwork Construction

Time:2019/01/21

 

The construction procedure of ADTO Formwork is similar to the traditional type of Formwork. The following processes are involved in the ADTO Formwork Construction:

 

 

1. Setting Up the Wall Reinforcing Steel

In this step, the wall reinforcing steel is used to form structure to the building, This reinforcement steel gives support to the concrete till it reaches 50% of designed strength. This steel mesh is pre-casted in the factory itself and can be easily erected on construction site.

 

 

2.Placing Formwork

As mentioned, ADTO Formwork is a ready-made one, Formwork is designed and manufactured in the factory itself as per the required sizes of slabs, columns, beams, staircase and other structural elements of the buildings. By Pin and wedge system Formwork is easily assembled on site. Formwork can be easily dismantled from the structure once the job is done.

 

 

3.Pouring Concrete

Once the Formwork is placed, Freshly made concrete is poured inside the Formwork to form the shape. Once the concrete gains required strength, the Formwork is dismantled from the structure.

 

 