How to prepare the ground foundation for standing tubes?
The ground foundation for standing tubes shall comply with regulations in the schemes and plans.
A When the erection height is less than 25cm, the ground shall be tamped and leveled to a flat level and then plank thick wood plate
witha a thickness of 5cm. If the wood scaffolding planks are 2m in length, they shall be placed vertically to the wall. And if 3m long,
parallel placed to the wall.
B When the erection height is between 25-50m, design the foundation treatment methods according to the ground endurance ratio on
site or use refilling and stamping methods level by level to meet the base requirements. The refilling can be wood backing or add another
layer of 20cm thick residue and the set concrete plate on the top and then top the plate of No. 12-16 groove steel.
C it is not advisable to direct put the standing tubes onto the scaffold boards or the working load bearing capacity of the backing
plates will be altered accordingly. It is easier for the deliverance of working load with a structure of back board scaffolding below.