A discreet checking of the erected scaffolding shall be done according to the regulated requirements.
- The door frame scaffolding structure shall comply with the planned requirements and designs. For the changes of some special frame parts, the size tolerance shall be adjusted within allowable ranges.
- The connection between the joints shall be reliable and sturdy and the torsion of the couplers shall be <40-60NM.
- The vertical ratio of the standing tubes shall be no more than 1/300 in the steel frame scaffolding system and the maximum vertical tolerance shall be within effective control.
- The horizontal tolerance of the longitudinal steel flat tubes shall be no more than 1/250 and the total frame length horizontal tolerance shall be no more than 50mm.
- The planking and protective measures on the working platform shall also in accordance with the above requirements.
- The frame scaffolding shall be routinely checked and inspected to see if there is any nullification. Only approval received can they be put into application.