How to Design the Outside Cantilevered Double Scaffolding in A Right Way

Time:2016/09/18

1, on a floor construction scaffolding using the outside of the next cantilever scaffold, its upright position should be staggered cantilever double beams, steel wire rope of scaffolding and rings, to take advantage of the ground double xenophobic scaffolding planks, cantilever double exclusive scaffolding.

 

 

scaffolding planks

 

 

2, according to the height of the tower floors of the building and unloading situation, every four layer set a unloading, suspension wire rope rings, a reinforced level 20 production, should not be less than 30 d, embedment depth and should hook structure reinforcement. Side beams, walls embedded rings and beams between the TAB on the set of wire rope, the 1.5 T gourd taut with 3 U card and a secure curved fixed basket screw tightening.

 

3, every step of the operational layer must be put with bamboo basketry;

4, i-steel, wire rope, rings embedded, processing, fixed and Rachel should send the specialist is responsible for the implementation, inspection, it is forbidden to buy without leakage, it is forbidden to touch each node.

Second, the cantilever double scaffolding, and note

 

1, outside on a floor construction scaffolding using the outside of the next cantilever scaffold, its upright position should be staggered cantilever double beams, steel wire rope of scaffolding and rings, to take advantage of the ground double exclusive scaffolding, cantilever double scaffolding with pierced steel plank with hooks.

 

 

scaffolding planks

 

 

2, according to the height of the tower floors of the building and unloading situation, every four layer set a unloading, suspension wire rope of the rings, using level reinforced nu 20 productio, embedment depth should not be less than 30 d, and should hook structure reinforcement. Side beams, walls embedded rings and beams between the tab on the set of wire rope, the 1.5 T gourd taut with 3 U card and a secure curved fixed. 