How to Carry Out the Erection Process Of Scaffolding System
A) before the erection of preparation
1. The technical personnel to the scaffold erection and site management personnel for technical, safety disclosure, not attend clarification personnel shall not participate in the erection work; Scaffolding, personnel must be familiar with the design content of scaffold.
2. The steel pipes, fasteners, scaffolding, gym, safety net of material, such as quality, quantity, counting, checking and acceptance, to ensure that meet the design requirements, and unqualified components shall not be used, shall not be connected when materials are not neat, different materials, different specifications of the materials and components shall not be used on the same scaffold.
3. Remove the erection site of sundry, set-up, under the high slope should monitor the stability of the slope, the slope on the cliff stone processing, and alert by designated personnel.
4. According to the height of the scaffold erection and erection site gay love situation, to deal with scaffolding foundation, according to the design requirements after confirm qualified, pay-off.
5. Involved in the scaffold erection and site management personnel's physical condition to be confirmed, who are not suitable for engaging in the operations in which high personnel shall not be engaged in scaffolding set-up and the field of construction management.
(2) the erection requirements
1. Scaffolding set-up must be in accordance with the approved plan and site of disclosure requirements, it is forbidden to cut corners, strictly abide by the set-up process and must not be deformation or corrected material as a stud.
2. In the process of the scaffold erection, site must have the skilled technical personnel shift instruction, and are certified safety inspection supervision.