How to Calculate How Much the Scaffolding Will Be Needed in the Construction

Time:2016/09/06

 

Frame Scaffolding is indispensable equipment in modern construction, on scaffolding, before, we must complete the dosage of the scaffolding business accounting. So, how can we accurately calculate the amount of engineering needed scaffolding?

 

frame scaffolding

 

1. Building a comprehensive scaffolding outdoor floor above the construction area of calculation according to the building. Building height is referred to like the design of the outdoor floor to the height of the eaves (not including the parapet, roof water tank, the eaves, stair height). The basement (half basement) scaffold according to its construction area of calculation.


2. Scaffolding and cast-in-place reinforced the concrete foundation, the width is greater than 3.0 m band base, can be calculated according to the foundation base area and scaffolding, not to deduct wall of area, nor plus foundation transportation area.


3. Not according to the construction area of calculation of the composite scaffold independent column, reinforced concrete wall, and impending single beam, continuous beam single scaffold:


1) Independent of brick, stone, reinforced concrete column, the column structure of outer circumference and 3.6 m times column high area computation; Using single frame scaffold height below 3.6 m, fixed deduction safety net; More than 3.6 m, double row scaffolding quota to corresponding height.


2) The cast-in-place reinforced concrete wall, according to the wall structure length times height with area computation, to paraphrase the corresponding height of double-row scaffold quota to deduct safety net.

 

3) The cast-in-place reinforced concrete beam or continuous beam, the outdoor floor surface is designed according to the length of the beam structure is multiplied (or floor surface) to the height of beam end face with area computation, to paraphrase the corresponding deduct the net height of the double-row scaffold project, that is associated with the top end frame scaffolding column is no longer calculate scaffolding.